Construction Process

 

Construction will be completed in two stages, Civil Works followed by Main Works.

Civil Works

Civil works, also known as early works, commenced at the beginning of September 2023 and are now complete.

We contracted Delta Group to undertake civil activities, which involved site preparation, foundation works, bulk excavation, implementation of waterproof membrane and establishment of concrete slab on ground. These preliminary tasks were carried out to ensure the site is ready for the first stage of main construction works, which are now underway.

Main Works

Now that civil works are complete and pre-sales requirements have been met, the main building works have commenced. The overall construction program for The Albertine expected to be completed in mid-2027.

Main works construction will be carried out by Mirvac Construction in the following stages:

1. Main building structure
2. Facade
3. Services and finishes
4. Landscaping

Mirvac Construction

Mirvac is an integrated property company with its own in-house construction team. Mirvac Construction will be responsible for the delivery of this project. With 50 years of experience in managing construction projects and ensuring the highest level of oversight and supervision, we are committed to delivering a positive outcome for the project and the community.

Mirvac Construction is currently the first business in Australia to be awarded the highest possible 5 Gold Star iCIRT rating by Equifax, and the only business to have achieved this rating two years in a row, which is a testament to our ability to deliver safe, reliable and compliant building outcomes.

 

Managing Construction

Construction activities are subject to conditions imposed by City of Port Phillip Council. Further to this, Mirvac will implement the following controls to ensure the effects of construction are mitigated:

- Site management plans
- Traffic management plans
- Noise and vibration monitoring
- Dust management monitoring
- Environmental management plans
- Waste management plans
- Sediment and erosion control plans
- Street cleaning as required

Operation Hours

The planning permit in place currently allows building works to occur:

- Between 7am and 6pm, Mondays to Fridays inclusive.
- Between 9am and 5pm, Saturdays

These hours are in line with the City of Port Phillip Council’s regulations. If, from time-to-time activities need to take place out of hours we will obtain the relevant permits from Council and we will notify near neighbours of these in advance.

Register for updates

Community engagement is an important part of Mirvac’s commitment to being a good neighbour, and we look forward to seeking your feedback and keeping you informed as construction progresses. To receive community updates, including future consultation activities, please register your interest via our community updates form.